It
was an emergency. Another emergency. When you're up to there in alligators
you can't hardly drain the swamp, but we had to catch this alligator
in a hurry.
Transmission Division came to us with
a problem with spot welds. They knew we had developed an ultrasonic
method to test spot welds and they called us immediately to solve their
problem.
Spot welds were being used to hold
certain brackets to the interior of the steel cases of torque converters
for automotive transmissions. Torque converters take the power of the
engine and transmit it through an impeller and a turbine combination
to the gears and bands in the automatic transmission so that the power
can get smoothly to the drive wheels of the automobile or truck. The
torque converter case is two pieces of sheet metal which come together
in the shape of a bagel, about 356 mm (14 in.) in diameter, which has
been sliced and put back together. Continuing the analogy, all the interior
dough has been hollowed out to permit the insertion of the impeller
and the turbine.
No
amount
of adjusting current and voltage could produce good welds on this
new model of torque converter.
At any rate, the spot welds on this
bracket inside one side of the converter case were failing. No amount
of adjusting current and voltage could produce good welds on this new
model of torque converter.
Using new developments based upon
previous work by other engineers in Philadelphia, Tony Mansour found
that he could test these spot welds and predict future failures. Based
on this success in the technical feasibility study on a few converter
cases, Mansour and I were invited to visit the transmission plant, recommend
a manufacturing feasibility study and then suggest automated implementation
equipment namely a big, expensive system.
After talking with the very worried
engineers and their harried managers, Mansour and I were taken into
the plant to observe the spot welding equipment in action. The equipment
was massive and heavy duty. There were two spot welding heads mounted
on a large piston running vertically which brought the heads down to
touch and clamp the bracket to the section of the converter case. These
two heads were placed symmetrically at three and nine o'clock with respect
to the shaft hole in the center of the circular section of this half
of the converter case "bagel."
The end of the piston was insulated
from the rest of the machine so the current, when introduced into the
spot welding heads at the bottom of the piston, would flow through the
welding heads, through the two layers of sheet metal to be spot welded
and into the corresponding lower spot weld heads. A region of metal
was supposed to melt where the current passed from one metal sheet to
the other and then refreeze into a nugget when the current was turned
off.
The metal parts were placed into
the jigs correctly, the piston moved up and down properly and the current
flowed.
The current was so many thousands
of amperes that it had to be carried by large amounts of copper. Since
the current source was stationary and the piston tip which required
the current moved up and down with a sizable throw, the cable for the
current had to be flexible. For symmetry to the two spot welding heads,
the current was brought to the piston head by two sets of conductors
from the two sides. To be flexible and to have a large surface area
to carry the large alternating current, the conductors were multiple
layers of thin sheets of copper separated by air gaps of about ten times
their thickness. These sheets of copper were clamped to the piston at
the center and to two electrical buses outboard. To permit the flexibility
for the vertical motion of the piston, the copper sheets were extra
long and drooped down in a sort of catenary shape on the two sides of
the piston. As the piston raised and lowered, one could imagine looking
at the cables of a suspension bridge flex if one pier moved up and down.
Mansour and I watched this welding
process intently. Soon the solution became obvious. What was happening
was this: with the pistons in the lowered position, the bottom copper
catenary sheet was touching the frame of the machine and grounding out.
Occasionally (but not on every stroke), sparks would fly as the current
came on.
The NDT solution was to do no NDT
at all. First, we ordered an electrician to tape large pieces of 13
mm (0.5 in.) thick rubber pad to the frame of the machine under the
copper catenary conductors. Second, we recommended that the engineers
adjust the heights of the various elements so that the copper would
not droop so far, leaving the copper catenaries up in the air where
they belonged. Good spot welds resulted when the current was subsequently
set to its design specifications.
The root problem here was the old
fashioned Taylor theory of management which was in use in all of American
industry for so many years (see Walton [1986] for more information).
Under the Taylor regimen, the workers on the floor just moved things
and had no intellectual input into a process. Even if the workers had
reported sparks in the wrong place, they would not have been listened
to by the foremen and would not have been believed. Indeed, they would
have been reprimanded for interfering and not producing. Taylor did
not want workers to have any training, so they would not have even been
instructed that sparks or electrical lines grounding out were undesirable.
The engineers would not have been empowered to ask the workers any questions
of substance.
Taylor kicked all the responsibility
upstairs to the engineers and then further upstairs to their managers.
What was the responsibility of the engineers? The engineers would have
drawn up the process with the welding heads touching the piece parts
in the right place and the current being correct for the thickness of
metal and would have assumed that their spot welder would work well
in a turnkey fashion with its manufacturer being the responsible party
("upstairs" from them). It would be very likely that the engineers'
analysis did not go deep enough (before the introduction of Ishikawa
fishbone diagrams in the 1980s) to even discuss a possible short circuit
in a failure modes and effects analysis. Who would have thought it,
anyway? But even in the presence of acknowledged difficulties, the engineers
did not have the time or did not take the time to go to the plant floor
and look at what was really happening. And, under Taylor, the managers
were absorbing blame but doing nothing intellectually creative. The
alligators were taking over the factory as well as the swamp.
For further study of the proper management
of NDT in the context of industry and total quality management, and
for further study of the cost of quality when detrimental things occur,
one would be advised to take short courses on these subjects when they
are offered at ASNT national conferences.
References
Mansour, T.M., "Ultrasonic Inspection of Spot Welds in Thin Gage
Steel," Materials Evaluation, Vol. 46, 1988, pp. 650-658.
Walton, M., The Deming Management
Method, New York, Putnam, 1986.