|
Radiographic testing (RT) is commonly used
for inspecting welded sections on offshore drilling platforms.
This technique, however, is subject to radiation regulatory
requirements, which impose restrictions on other production
activities and logistics. This month's column shows how one
company dealt with these issues by using mechanized ultrasonics
(UT), and completing the inspection in a timely fashion.
G.P. Singh
Associate Contributing Editor
|
Figures 1-3
Figures 4-6
Figures 7-8
Editor's Note: As referred to by the authors in this article, mechanized ultrasonic
testing involves the use of a continuously moving scanning machine to
test welded seams in large-scale operations.
Background
Major
offshore drilling projects are being carried out around the world. Drilling
platforms used
in petroleum exploration are subjected to extensive inspection during
their construction to ensure the integrity of components. The main load
bearing components of such a platform are the legs and piles. These
are usually tubular sections welded together, with the lower sections
having larger diameters and thicker walls than the upper sections. These
tubular sections are constructed from plates rolled into cylindrical
shapes, with a submerged arc weld forming the long-seam. The section
thus formed can then be joined to other sections by submerged arc welding
of circumferential seams. See Figures 1
and 2.
For both the manufacturer and the customer this was
their first experience in effective application of mechanized
UT...
Traditionally, both of these seams (longitudinal and circumferential)
have been tested using RT. Results of RT (using Co-60) for thicknesses
up to 100 mm (4 in.) of steel are doubtful at best, but not many facilities
have linear accelerators, which can produce better quality X-ray images.
Under these circumstances, and using Co-60, the standard 2-2T sensitivity
is fuzzy at best. At normal production rates about 1 or 2 long seams could
be radiographed in an eight or twelve hour shift.
A large manufacturing company was awarded the contract
to build two offshore drilling structures in an 18-month period. This
would be a significant burden on their radiography department, but more
important were the logistics of timing and handling. Radiation regulatory
requirements require that certain areas be roped off while performing
RT. This meant that the very large sections of legs and piles would
need to be lifted away to a dedicated area, or RT would need to be carried
out in the shop during the night shift, when the access restrictions
imposed by roping areas off would have the least effect on production
activities. To address this potential bottle-neck, the manufacturer
requested that the customer consider mechanized ultrasonic testing (UT)
as an option to RT. The customer agreed to consider the option, provided
that the technique was proven to be as reliable as RT.
This paper describes the techniques adopted and
the experiences gathered, as UT eventually supplanted RT and allowed
the project to be completed in a timely fashion.
Code Requirements
Nondestructive testing (NDT) on the project was regulated by the dictates
of the American Petroleum Institute's Recommended Practice for Offshore
Structural Fabrication and Guidelines for Qualification of Technicians,
known as API RP2X, as interpreted by the customer (API 1996). In order
for UT to be applied the procedures would need to meet the requirements
of API RP2X.
This API Recommended Practice document requires
inspection of 100 percent of all longitudinal seams and 10 percent of
circumferential weld seams. Although the API RP2X document gives extensive
descriptions of general advantages and limitations of ultrasonics, its
main coverage is devoted to technical recommendations for manual applications
of ultrasonic testing and methods for qualifying ultrasonic technicians.
This concern for technique and
operator ability is based primarily on the traditional application of
UT to the very difficult T, K, and Y joint configurations. Application
of UT to the simple symmetric butt weld configurations used for this
project would place less demand on operator ability to plot indications
than in the complex T, K, and Y geometries. As with most such documents,
however, API RP2X has not given special consideration to the specific
aspects of mechanized UT. To address the absence of specific guidance
in the API RP2X document, both the manufacturer and the customer developed
a qualification program to allow the introduction of mechanized UT.
For both parties involved this was the first experience in effective
application of mechanized UT, and therefore considerable debate and
cooperation was required for this new venture.
This became a multistage program, requiring:
- developing a procedure and techniques to inspect
the range of butt welds proposed for inspection
- training operators on the use of the equipment
and application of the techniques
- construction of a mock-up of a weld with typical
anomalies
- qualification of the equipment and technique
on the mock-up
- moving to the field and performing trials of
the equipment, techniques, and operators to qualify the entire concept,
including operators
- correlating ultrasonic and radiographic results
to establish a confidence in the system with decreasing dependence
on radiography. This would mean moving from 100 percent radiography
and 100 percent ultrasonic testing to zero percent radiography and
100 percent ultrasonic testing, with the percentage of radiography
being reduced in several stages.
Every effort was made by both parties to observe
the intent of the API Recommended Practice document, while recognizing
that strict adherence to the document was not possible due to its lack
of information on mechanized UT information. As a result of the extensive
efforts to ensure that the results of RT were the minimum expectations
of the system, a significant advance in technology was possible.
To ensure maximum integrity, the manufacturer agreed
to use the Level A acceptance criteria in Appendix D of API RP2X. This
is based on workmanship quality and is not related to the component's
fitness-for-purpose. These criteria would more closely relate to the
radiography acceptance length criteria. These acceptance criteria, however,
base evaluation response on a 1.5 mm (0.06 in.) diameter side drilled
hole at the depth of concern. This applies to a 25 mm (1 in.) thick
section as much as to as a 105 mm (4 in.) thick section. Effectively
a 25 mm (1 in.) thick section is evaluated to a hole six percent of
wall thickness, whereas a 105 mm (4 in.) section is evaluated to a hole
1.5 percent of wall thickness.
This is in contrast to radiography, where the image
quality indicator (IQI) varies with the thickness,while trying to maintain
a similar sensitivity with respect to wall thickness. In a 25 mm (1
in.) section requiring a #25 penetrameter (ASME source side) the essential
hole is the 2T and is 1.3 mm (0.05 in.) in diameter. This represents
about five percent of the wall thickness. For a 64 mm (2.5 in.) wall
the source side IQI is the #40. The #40 2T hole is 2 mm (0.08 in.) in
diameter, or about three percent of the wall thickness.
Technique
The UT technique developed was a combination of rastered pulse-echo
inspection coupled with time of flight diffraction (TOFD). This ensured
that the entire weld volume was inspected with the pulse-echo probes,
paying special attention to the weld bevel fusion faces, with TOFD providing
extra coverage for the volumetric anomalies and off-angle planar anomalies
not optimally orientated for the pulse-echo probes.
Figure
3 shows a typical set-up. This uses two
pair of 45° probes for the full skip, a pair of 60° probes for
the half skip, and a TOFD pair set for nominal 65° refraction in
compression mode. The data for the TOFD pair are collected with the
probes placed symmetrically on either side of the weld centerline. For
the pulse-echo probes a raster scan is used in which the probes are
moved about 10 mm (0.4 in.) perpendicular to the weld centerline after
each scan, with five such scans being made to cover the inner and outer
third of the fusion faces.
In addition to the full volume being ultrasonically
tested, an additional NDT was carried out on both the inside and outside
surfaces, using magnetic particle inspection. This ensured that fine
surface anomalies that might be masked in the unground weld cap could
be detected. As well, a manual UT inspection using 0° compression
mode was used to ensure no that laminations were present in the plate
where the mechanized inspection was carried out.
System Integration
R/D Tech designed the full integration of automatic UT inspection system
for Daewoo Heavy Industries Co. Ltd. The procedure, designed by Material
Research Institute, requires that three to five linear scans, depending
on the wall thickness, are made with a different offset from the weld
centerline. Figure 4
illustrates the diagram of system integration. The components of the
system are:
- a magnetic strip is located at a constant offset
from the weld centerline, the scanner follows the magnetic strip and
moves along this axis with its magnetic wheels (see Figure
5); an arm on the scanner positions the probes at a correct offset
from the weld centerline
- the UT acquisition system synchronizes the pulses
to the probes with the position encoders from the scanner. The encoded
ultrasonic signals will permit generation of A-scan, B-scan, C-scan,
and volumetric presentation of the information
- the system is completed by a motor drive unit
which delivers the power to the scanner, a pump for local immersion
UT coupling, and an optical disk for data files archive.
After the operators had become familiar with the
equipment, a 4 m (13 ft) longitudinal seam on a 70 mm (2.75 in.) thick
section could be inspected and evaluated within one hour. This was a
significant improvement over RT.
Qualification and Trials
Calibration blocks using side drilled holes and slots were made by the
manufacturer and used to develop and optimize the techniques. Mock-ups
were made by the manufacturer and used to qualify the techniques and
operators.
The mock-ups were long-seam welds made with welding
anomalies imbedded at various depths and locations. The techniques were
confirmed and qualified on the mock-ups. Figure
6 shows a sketch of the mock-up weld used for qualification with
the positions of the imbedded anomalies. With the exception of the porosity,
"anomalies" were made using ceramic inserts approximately
4 ´ 45 mm (0.15 ´ 1.75 in.). Figure
7 illustrates the processed data from the pulse-echo probes. Customized
software allowed the data collected to be presented in a typical "top/side/end
view" format. Figure
8 illustrates the A-scan and B-scan representation of the TOFD channel.
Results
After the technique had proven it could detect the anomalies in the
mock-up, there was a transition from RT to mechanized UT. This involved
inspection of actual production welds using both methods. During this
transitional period only, all significant indications found initially
by RT were also detected subsequently by mechanized UT. As the transition
progressed, and less RT was being performed, RT was carried out where
indications had been located initially by mechanized UT. All indications
located by mechanized UT were confirmed by manual UT but in many cases
they could not even be detected by RT. This did not negate the validity
of either NDT method, but merely reflects differences in the ability
of the methods to detect different types of anomalies.
Findings and Conclusions
Laboratory techniques, which were verified on customer mock-ups, were
used to phase out the use of RT for this application. Further requirements
to satisfy the customer's concerns involved site trials. Therefore,
several hundred welds tests by mechanized UT were compared with tests
performed by RT. It was seen that all significant anomalies found using
RT were also detected using mechanized UT.
It was concluded that mechanized UT was an effective
replacement for radiography in this instance and offered a comparable
confidence level in probability of detection of all significant anomalies.
Acknowledgments
The authors would like to thank Chevron Oil for their help in adapting
this new technology and for the image of the Lomba Project Platform
used in Figures 1 and 2. We would also like to thank R/D Tech and Daewoo
Heavy Industries for the images of equipment and the report results.
References
API 1996: Recommended Practice for Ultrasonic and Magnetic Examination
of Offshore Structural Fabrication and Guidelines for Qualification
of Technicians, 3rd edition, November 1996, American Petroleum Institute,
Washington DC.
* Materials Research Institute, 368 Lexington Rd., Waterloo, Ontario,
Canada N2K 2K2; (519) 886-5071; fax (519) 886-8363; e-mail ginzelea@wat.hookup.net.
+ R/D Tech, Inc., 4495, Wilfrid-Hamel Blvd, Québec
City, Québec, Canada G1P 2J7; (418) 872-1155; fax (418) 872-5431;
e-mail glegault@rd-tech.com.
Copyright © 1998 by
the American Society for Nondestructive Testing, Inc. All rights reserved.
[ Materials Evaluation
]