November
5, 2002
Hollis
Humphries
TNT
Editor
ASNT
P.O.
Box 28518
Columbus,
OH 43278
RE: Possible Errors in TNT-Volume 1, Edition 4 (October 2002)
Pertaining to Non-Nuclear ASME Codes.
Dear Mr. Humphries:
After review of the above stated document, it is
my opinion that the information presented in this article contained
several errors and/or partial facts that should be clarified to your
readers. In my opinion, these items are listed as follows:
• Page 2 – “Code references to visual requirements
are usually for the Third Party Code (sic) Inspector”
This
statement ignores the fact that mandatory written quality control
programs are required in all ASME construction codes, which stipulate
that visual examinations be conducted by the Manufacturer.
See UG-90 in ASME VIII. (Note the emphasis on “examination” versus
“inspection” which is normally very confusing to many NDE practitioners).
• Page 2 – “NDE requirements are determined
in contract documents”.
This
is partially true - however, the ASME Code mandates certain NDE requirements
regardless of contractual rules, based on service or thickness (example:
See UW-11 and UCS-57 of ASME VIII) or design conditions (example:
See UW-12 of ASME VIII and PW-11 of ASME I).
• Page 3 – “Sensitivity”
1) Reference to Table “T-272” should be
“T-276”.
2) “This usually applies to shimmed hole type
penetrameters (sic)” - This is incorrect. The –15%/+30% rule applies
to all IQI’s, whether they are placed across the weld or on
a shim. The +30% upper density restriction may be exceeded (up to
4.0 H&D density, maximum) if a hole-type IQI is shimmed.
3) “NOTE: In the case of Section VIII of the
Code, un-sharpness values are guidelines, but not to exceed 0.07 in
(1.75mm).” - This is incorrect. There are no upper limits on unsharpness
in ASME VIII; T-285 of ASME V is only a guide. The upper restriction
of 0.07 in. is from ASME I, PW-51.
• Page 3 – “Relevant Indications”:
“ASME Construction Codes define two types of indications -
relevant and nonrelevant.”
This
is partially true. The definition of what constitutes relevant
and non-relevant indications is only provided for MT/PT and Appendix
4 in ASME VIII for rounded indications. For all other methods, “relevant”
and “non-relevant” indications are not defined. The general term “imperfections”
is used in UW-51/UW52 for RT, and also in Appendix 12 for UT.PW-51
and PW‑ 2 of ASME I also follow this language.
• Page 4 – “Proper Application of non-destructive
testing in accordance with codes such as the ASME Boiler and Pressure
Vessel Code guarantees the safely and reliability of materials and
fabrications during manufacture, maintenance, and performance”.
I Seriously believe that the authors of this article
should rethink any statement that “guarantees” the safety of equipment
built to the Code, even if the proper NDE is applied. The Manufacturer’s
Data Report for each item does not “guarantee” safety – it simply
states that the manufacturer and Authorized Inspector believe that
the item was built to the Code.
• Page 4 – Table 2 - “VT”:
The
use of the acronym “VT” may lead some to believe that formal visual
examination (per ASME V Article 9) with personnel qualifications and
written procedures is required. This is untrue. Again, the term visual
“examination” (conducted by the manufacturer) versus “inspection”
(conducted by the Authorized Inspector) should be clarified here as
to who is responsible to do what. It should also be clearly noted
that ASME VIII and/or ASME I do not specify mandatory minimum
training and certification requirements for Quality Control (visual)
examination personnel.
In
the same vein of thought, an article on page 1228 of Materials
Evaluation in this same issue (October 2002) contains an advertisement
for the API UT Examiner Program. This ad states – “API 510 and 570
make the use of qualified UT Examiners “mandatory”
(their bold, not mine). This is untrue. The requirement for utilizing
industry-qualified UT operators will become mandatory in December
2003 (see Para. 5.5 of API 510 and Para. 8.2.6 of API 570).
Additionally,
your readers should be advised that API 510 and API 570 both allow
alternative equivalent UT Examiner qualifications if approved by each
owner/user. Therefore, the use of only "API – certified" UT
personnel is not mandatory now, nor will it be in December 2003. If
approved by the owner-user, ACCP, AWS, or other “equivalently qualified”
UT personnel may be used.
Thank
you for the opportunity to allow me to comment on this information.
Please contact me at your convenience if you require any further information
or have any questions.
Sincerely,
Tim Schindler
Managing Partner
Schindler & Associates
ASNT Level III
La Grange, Texas
November 13, 2002
Tim Schindler
Schindler & Associates
La Grange, TX 78945
Dear Mr. Schindler:
Thank you very much for your letter
of November 5, 2002. The NDT
Technician appreciates your concern regarding possible errors
in Vol. 1, Issue No. 4 pertaining to non-nuclear ASME codes. Your
comments regarding the article have been forwarded to reviewers of
the material and we look forward to their response on this important
matter. A copy of your letter has also been forwarded to the staff
of Materials Evaluation
for their action. On behalf of our readers, thank you again for your
interest and concern.
Best regards,
Hollis Humphries
TNT Editor
Response to Letter From Tim Schindler on NDT Technician Article
Page 2 Schindler Comment on: “Code references to visual requirements
are usually for the Third Party Code (sic) Inspector”
His comment: “This statement ignores the fact that mandatory written quality
control programs are required in all ASME construction codes, which
stipulate that visual examinations be conducted by the Manufacturer.
See UG-90 in ASME VIII. (Note the emphasis on “examination” versus
“inspection” which is normally very confusing to many NDE practitioners).”
What he says here is also partially
true. The Code, however, has no specific requirements for visual examination
that spell out, how a component is to be examined, what acceptance
standards apply to it and who can do the examination. Each manufacturer
must develop these as part of their program. There are no qualification
requirements for whomever does visual examinations as there are for
personnel performing radiographic and ultrasonic examinations in Section
I and VIII. On the other hand these Codes have very specific inspection
duties for the Inspector. When the Code refers to Inspector, it is
referring to an Authorized Inspector as used in Sections I and VIII.
Page 2 Schindler Comment on: “NDE requirements are determined
in contract documents”.
His comment: “This is partially true— however, the ASME Code mandates certain
NDE requirements regardless of contractual rules, based on service
or thickness (example: See UW‑11 and UCS-57 of ASME VIII) or
design conditions (example: See UW-12 of ASME VIII and PW-ll of ASME
I).”
I think
he really means UW-11 instead of UW-12. His comment ignores the fact
that every purchase of a pressure vessel or boiler begins with a contract.
That contract will identify what edition of Codes are applicable,
since jurisdictions may not all reference the latest published edition
of the Code. Legislatures usually must approve laws that mandate particular
requirements. However, each jurisdiction and owner may have additional
requirements or the architect/engineer may have additional requirements.
As an example, Section I does not require radiographic examination
of boiler tubes as they meet exclusion requirements, but on most,
if not all, power or recovery boilers, radiography is performed during
fabrication and construction on these tube welds.
Page 3 Schindler Comment on: “Sensitivity”
His comments:
“1)
Reference to Table “T-272” should be “T-276”.”
His comment is correct.
2) “This
usually applies to shimmed hole type penetrameters (sic)”
“This is incorrect. The -15%/+30% rule applies
to all IQI*s, whether they are placed across the weld or on a shim.
The +30% upper density restriction may be exceeded (up to 4.0 H&D
density, maximum) if a hole-type IQI is shimmed.”
His
comment is basically correct. The requirement for the -15% or +30%
apply for both types of IQI’s. However, shims are only used on hole
IQI’s and the +30% density level can be ignored when shims are used
as long as a 4.0 density is not exceeded.
3) “NOTE: In the case of Section
VIII of the Code, un-sharpness values are guidelines, but not to exceed
0.07 in (1.75 mm).” This
is incorrect. There are no upper limits on unsharpness in ASME VIII;
T-285 of ASME V is only a guide. The upper restriction of 0.07 in.
is from ASME I, PW-51.
His comment is correct. They are requirements
for Section III work, however.
Page 3 Schindler Comment on: “Relevant Indications”
“ASME Construction Codes define two
types of indications — relevant and non-relevant.”
His comments: This is partially true. The definition of what constitutes
relevant and nonrelevant indications is only provided for MT/PT and
Appendix 4 in ASME VIII for rounded indications. For all other methods,
“relevant” and “non-relevant” indications are not defined. The general
term “imperfections” is used in UW-51/UW52 for RT, and also in Appendix
12 for UT. PW-51 and PW-52 of ASME I also follow this language.
The
determination of relevant and nonrelevant indications is basic in
the NDT methods. Training outlines in SNT-TC-1A and training course
materials define causes of indications and even add false indications
to the list. The Section VIII Code may only mention these in MT, PT
and RT rounded indications sections, but it is clear from the definitions,
ASME Section V, Article 30 that an imperfection is a “departure of
a quality characteristic from its intended condition”, a relevant
indication. The Code does not intend that evaluation be applied to
nonrelevant indications or nonimperfections that may be part of the
material’s characteristics or the physical makeup of the component
such as a drilled hole, weld root penetration, grain boundries or
other feature that is part of the design or results from the fabrication
materials or methods.
Page 4 Schindler Comment on: “Relevant Indications”
Page
4 — “Proper application of non-destructive testing in accordance with
codes such as the
ASME Boiler and Pressure Vessel Code guarantees the safety and reliability
of materials and fabrications during manufacture, maintenance, and
performance”.
His comments: I
seriously believe that the authors of this article should rethink
any statement that “guarantees” the safety of equipment built to the
Code, even if the proper NDE is applied. The Manufacturer’s Data Report
for each item does not “guarantee” safety — it simply states that
the manufacturer and Authorized Inspector believe that the item was
built to the Code.
What was probably meant here is that
following the rules for the Code provides a greater assurance of safety.
However, the reliance on NDE alone to the exclusion of the other features
of the Code guarantees nothing. The safety of Code vessels and systems
has been demonstrated over the last few decades when all of the requirements
of the Code have been met.
Page 4 Schindler Comment on: Page 4-Table 2- “VT”
His comments: The use of the acronym “VT” may lead some to believe that formal
visual examination (per ASME V Article 9) with personnel qualifications
and written procedures is required. This is untrue. Again, the term
visual “examination” (conducted by the manufacturer) versus “inspection”
(conducted by the Authorized Inspector) should be clarified here as
to who is responsible to do what. It should also be clearly noted
that ASME VIII and/or ASME I do not specify mandatory minimum training
and certification requirements for Quality Control (visual) examination
personnel.
The Code Section referenced in Table
2, UG-90, provides requirements for both visual examination and inspection.
The application of the terms is consistent with the Code’s previously
described use of the terms “examination” and “inspection”. As with
any SNT-TC-1A program, the use of the term “VT” should be described
in the manufacturer’s quality program and its NDE procedures. Neither
ASME Section I or Section VIII require that the recommendations of
SNT-TC-1A be followed for NDE personnel qualification for any method.
The manufacturer can follow the recommendations as written in SNT-TC-1A
or can have another program.
Frank Sattler
Sattler Consultants, Inc.
ASNT Level III
ASME Boiler and Pressure Vessel Code, Subcommittee V – Nondestructive Evaluation
Contributor Response to Reader Comments on TNT
Article
I suggest a general statement
of explanation that the article “Using the ASME Boiler and Pressure
Vessel Code” is intended to provide a brief overview to create an
awareness of the type of nondestructive requirements involved. The
article is not intended as a comprehensive treatment of all the various
Code sections.
Page 2 Reader Comment on: “Codes references to visual requirements are
usually for the Third Party (sic) Code Inspector”.
I believe ASME Section
III subsections NF and NG require Visual Examination in accordance
with ASME Section V Article 9 and NF/NG provide acceptance criteria.
Perhaps Richard McGuire can check this.
“This is correct. NF and NG of ASME Section III require visual examination
by others than the third party inspector.”
Richard McGuire
Manager of Training, National
Board of Boiler and Pressure Vessel Inspectors
ASME Boiler and Pressure Vessel Code, Subcommittee V ‑ Nondestructive Evaluation
Chair: Subgroup General
Requirements, Personnel Qualifications, and Interpretations Subcommittee
IX - Welding and Brazing Qualifications
Page 2 Reader Comment on: “NDE requirements are determined in contract
documents”.
Concur with proposed
response; however, the reader also seems to miss that the statement
in the article is not in conflict with the code, but states that the
contract or purchase order references the appropriate code. The reader
seems to misinterpret the statement as somehow in contradiction with
the Code.
Page 3 Reader Comment on: “Sensitivity”
Comment 1: is correct,
this is a typo and should have been Table T-276.
Comment 2: The reader is
correct about the provision of the code.
Page 3 Reader Comment on: “Relevant Indication”
Concur with proposed
response. Additionally, ASTM E 1316 “Standard Terminology for Nondestructive
Testing defines Relevant Indication as, “an NDT indication that is
caused by a condition or type of discontinuity that requires evaluation.”
Basic to the NDT industry is that relevant indications are those specified
in the applicable acceptance/rejection criteria.
Page 4 Reader Comment on: “Code guarantees the safety….”
Concur with reader
comments. I would have appreciated the opportunity to review the final
draft, and would have flagged this too.
Page 4 Reader Comment on: Page
4-Table 2- “VT”
Concur with proposed response.
Thanks,
Bill Plumstead
PQT Services, Inc.
Greenville, South Carolina